framing 1Well, another week has passed and it was a great week at the new facility. Lots of man/woman hours volunteered, money donated, and CHAIRS WERE PURCHASED AND DELIVERED!

 

So here is the rundown of what happened this week:

 

  • All the walls were framed and installed.
  • Stage was framed. Prepare, it’s a big stage!
  • Insulation was installed.
  • Nursery and sound booth built.
  • Some of the electrical and lighting was ran.
  • About 95% of all sheet rock was hung.
  • Chairs were assembled.

 

 

As you can see, it’s been a busy week, but highly productive. Watching the church build a church has been very exciting forframing 2 me. We have a lot left to do, but at this pace we are going to be our new home very soon.

 

Don’t stop praying, serving, and giving. All three are vital to the success of this building!

 

wall2Find life…live grace…become hope.

 

pBen